arbitration / adr news

Ghana hit with $134m judgment debt for cancelling GCGP's power agreement 

14 February 2021


The International Court of Arbitration has awarded a cost of $134 million and an interest of $30 million against the Government of Ghana over the cancellation of an Emergency Power Agreement with GCGP limited.

The Contract was cancelled under the former Energy Minister Boakye Agyarko as part of several other energy contracts cancelled by the NPP on the basis that the country did not need those power agreements.

The ruling by the International Court of Arbitration ordered the government to Ghana to pay to “GPGC the full value of the Early Termination Payment, together with Mobilization, Demobilization and preservation and maintenance costs in the amount of US$ 134,348,661, together also with interest thereon from 12 November 2018 until the date of payment, accruing daily and compounded monthly, at the rate of LIBOR for six-month US dollar deposits plus six percent (6%).”

The Government of Ghana was also to pay GPGC an amount of “US$ 309,877.74 in respect of the Costs of the Arbitration, together with US$ 3,000,000 in respect of GPGC’s legal representation and the fees and expenses of its expert witness, together with interest on the aggregate amount of US$ 3,309,877.74 at the rate of LIBOR for three-month US dollar deposits, compounded quarterly.”


Source: GhanaWeb








African Arbitration Association, P.O. Box 695, Nyarutarama, KG 9 Av. No. 66, Kigali, Rwanda

Contact us here

Privacy Policy  | Directory Terms of Use© 2018 African Arbitration Association


DISCLAIMER: No responsibility for loss occasioned to any person acting or refraining from action in reliance on or as a result of the information in or omitted from this website can be or is accepted by the AfAA, its officers, board members, employees or any other persons affiliated with the AfAA.